Otay Water Treatment Plant Upgrade and Expansion
Back to Projects
WaterTreatment - Conventional

Otay Water Treatment Plant Upgrade and Expansion

San Diego$35 million

Owner

City of San Diego

Location

San Diego, California

Value

$35 million

Completion

2005

Contractor

F.H. Paschen/SN Nielsen

Designer/Engineer

Separation Processes, Inc.

Project Overview

The City of San Diego Water Department selected Butier Engineering, Inc. to provide construction management, field engineering, administration, and inspection services for the Otay Water Treatment Plant Upgrade project. This upgrade and expansion project is under the City’s Capital Improvement Program. The Otay plant is a critical component of one of the nation’s largest systems for storing, treating, and delivering water to residents and businesses.

Scope of Work

  • Construction and installation of piping (48″ overflow and 18″ storm drain piping) and facilities for a membrane filtration system
  • Mass grading and construction of two 7 million-gallon treated water (clearwell) reservoirs (DYK prestressed concrete reservoirs)
  • Modifications to a raw water pump station
  • Installation of a chlorine vapor scrubber
  • Tie-ins to the CWA SD-7 raw water line and the lake water influent line

Awards & Recognition

  • American Society of Civil Engineers, San Diego Section — Award of Excellence

Explore More Projects