Lift Station 2 Force Main Rehabilitation Project
- Location:
- Laguna Beach
- Value:
- $2,945,000
- Completion:
- July 2019
- Owner:
- South Coast Water District
- Designer:
- Atkins North America, Inc.
- Contractor:
- Steve Bubalo Construction Co.
Butier Engineering, Inc. provided construction management and inspection services for the Lift Station 2 Force Main (LS-2 FM) Rehabilitation Project. Services included project controls, construction services, and project completion and closeout activities. The LS-2 FM Project consisted of the rehabilitation of the existing 6,400 foot, 20-inch diameter, polyurethane lined, polyethylene wrapped, Class 250 ductile iron pipe. It is located at 31104 Coast Highway in the City of Laguna Beach and ends at a point of connection inside the SOCWA Coastal Treatment Plant (CTP). The LS-2 FM is located within a 20-foot easement running northerly and adjacent to Aliso Creek and runs through portions of The Ranch at Laguna Beach, a resort with a 9-hole golf course. The scope of work for the LS-2 FM rehabilitation included the following:
- Sliplining using a 16-inch diameter high density polyethylene pipe
- Grouting the annular space
- Excavating 13 access pits
- Installation and operation of a full-length bypass system
- Replacing sections of pipe
- Installation of air vacuum release valves
- Removal and disposal of existing valves
- Installation of a surge tank
- Landscape restoration
- 545 (LF) of 10″ force main
- Sewer manholes and appurtenances
- Abandonment of Segerstrom Lift Station