Water Projects

Edinger Avenue Well Phase II Equipping

Owner:
City of Tustin, Public Works Department
Location:
Tustin, CA
Value:
$4.2 million
Completion:
2016
Photo Credit:
Mol Goodman Photography

Butier Engineering, Inc. provided project / construction management and inspection services for the Edinger Avenue Well – Phase II Equipping Project. The project was part of the City of Tustin’s Water Services Division, which is responsible for the production and safe delivery of domestic water to more than 14,100 service connections through approximately 172 miles of water mains. Butier staff coordinated with several agencies including the City of Tustin, City of Santa Ana, and Caltrans. Construction of the building and equipping of the pump included the following:

  • Installation of 225 LF of 12-inch diameter CML ductile iron pipe discharge water line
  • Connection to 12-inch ductile iron watermain
  • Installation of 162 LF of 18-inch diameter C-905 drain line
  • Connection to the existing storm drain
  • Placement of new onsite sewer manhole
  • Installation of 76 LF of 8-inch diameter SDR 26 sewer lateral
  • Connection to existing OCSD sewer manhole
  • Erection of 2,376 SF of CMU block wall with a metal roof building to enclose the well pump, electrical equipment and chlorine room