Wastewater Projects

Wastewater Projects

Voorhees Sewer Lift Station Upgrades

Owner:
City of Manhattan Beach
Location:
Manhattan Beach, California
Value:
$4 million
Completion:
Summer 2026
Contractor:
Myers and Sons Construction
Designer:
PACE Advanced Water Engineering

Butier Engineering, Inc. is providing construction management and inspection services for the lift station upgrades.  The rehabilitation of the Voorhees Lift Station includes the construction of a new adequate emergency storage wet well, new 350 gpm submersible pumps, reintegration of the existing station dry vault structure, installation of new mechanical and electrical equipment, and a new above-ground standby generator.  Additional scope of work items include a new SCE feed, a new above-ground CMU enclosed standby generator, new landscaping, and rehabilitation of the existing dry vault pit.

During construction, the existing sewer lift station will remain in operation for the most extended amount of time possible.