Voorhees Sewer Lift Station Upgrades




- Owner:
- City of Manhattan Beach
- Location:
- Manhattan Beach, California
- Value:
- $4 million
- Completion:
- Summer 2026
- Contractor:
- Myers and Sons Construction
- Designer:
- PACE Advanced Water Engineering
Butier Engineering, Inc. is providing construction management and inspection services for the lift station upgrades. The rehabilitation of the Voorhees Lift Station includes the construction of a new adequate emergency storage wet well, new 350 gpm submersible pumps, reintegration of the existing station dry vault structure, installation of new mechanical and electrical equipment, and a new above-ground standby generator. Additional scope of work items include a new SCE feed, a new above-ground CMU enclosed standby generator, new landscaping, and rehabilitation of the existing dry vault pit.
During construction, the existing sewer lift station will remain in operation for the most extended amount of time possible.