Chino Creek Well Field Raw Water Pipeline

Butier Engineering, Inc. provided construction management and inspection services for the Chino Creek Well Field Raw Water Pipeline project. The pipeline was installed as part of the CDA Phase III Expansion Project. Approximately 8,500 LF of PVC pipe ranging from 8” to 16” in diameter was installed within the City of Chino right of way…

Broadway Trunk Sewer Replacement/Rehabilitation Phase I-Microtunneling

Butier Engineering, Inc. provided resident engineering and inspection services during microtunneling operations for installation of approximately 6,132 linear feet of 36-inch vitrified clay pipe in East Broadway Avenue in the City of Long Beach. The project also included construction of eleven (11) standard 72-inch manholes, two (2) conflict reinforced concrete box structures, connection to the…